Renovating a Bathroom: The Right Order for Plumbing Works

In a bathroom renovation, the plumbing works follow this order: fix the layout, check the drains, strip out, run the new pipes, pressure test, waterproof and screed, tile, then fit the fixtures. Everything that will end up hidden must be decided, installed and tested before it is covered.
Planning a bathroom renovation in Paris or the inner suburbs? Call +33 6 86 08 78 68 (06 86 08 78 68 from a French phone), 7 days a week, 24 hours a day, or write to us through the contact page or WhatsApp. Many of our plumbers speak English, so you can discuss every choice in detail. Our tap, shower and toilet installation service supports you from feasibility to final connection.
Most budget and schedule overruns do not come from the price of materials, but from the order of works: a screed poured before the drains are validated, tiles laid before the leak test, a vanity unit ordered before anyone knows where the water supplies really are. Each of these mistakes is paid for in demolition.
Why the order matters more than the budget
In a bathroom, the pipes are buried in the screed and set into the walls. Once the tiles are down, any change means breaking them, so redoing the waterproofing, the screed and the finish. A mistake made in five minutes at the start costs days of rework at the end. That is why the layout must be fixed far earlier than most people expect.
The sequence, step by step
Step 1: fix the layout
Before stripping anything, settle the exact position of the shower or bath, basin, toilet, towel radiator and washing machine. Each fixture needs a water supply and a waste at a precise height and position. Choose the type of shower now too: an extra-flat tray, a walk-in shower and a bath do not need the same drains or the same screed height.
In a small Paris bathroom, think space-saving from the start: a compact wall-hung toilet, a shallow vanity unit, a made-to-measure shower to use an awkward corner, a sliding or pocket door.
Step 2: check the drains
The most decisive point, and the one most often discovered too late. A waste pipe works by gravity and needs a steady slope down to the soil stack. In an old building the stack is sometimes far away, and ceiling height and floor thickness limit what is possible. Moving a toilet or creating a walk-in shower far from the stack can be impossible without raising the floor.
If the natural slope is not enough, there are two options: a low platform that hides the pipes while keeping the right slope, or a pump (or a macerator for a toilet), to be decided before the layout is fixed. Have this feasibility checked before ordering anything.
Step 3: strip out
Removing the old fixtures and finishes exposes the pipes and reveals their real condition. Lead or galvanised steel pipes often turn up in older buildings. Since they are accessible, this is the time to replace them: our article on replacing lead and cast-iron pipes in Paris explains the choice. Plan for protecting the common areas (lift, stairs) and your flat, and for removing the rubble.
Step 4: run the new pipes
The plumber installs the new hot and cold supplies and wastes according to the validated layout. Add capped connections now for future appliances: a capped supply for a future washing machine costs little today, compared with a whole new job later. This is also when the electrics go in, strictly respecting the safety zones around water set by the French wiring standard NF C 15-100.
Step 5: the pressure test, the point of no return
Before anything is closed up, the system is put under pressure and monitored for several hours. It is the last chance to catch a faulty joint before it becomes inaccessible. A serious professional never closes up without this test. If someone suggests skipping straight on, that is a warning sign: a pinhole leak found under new tiles turns a detail into water damage.
Step 6: waterproofing and screed
Next comes the waterproofing system under the tiles (a membrane or liquid coating), essential for any tiled or walk-in shower, then the screed with the drainage slopes. A badly made slope at this stage gives a shower where water sits, impossible to fix without starting again. Respect the drying times.
Step 7: tiling, then fitting the fixtures
The tiler lays the finish, then the plumber installs and connects the sanitary ware and taps. Perimeter sealant completes the job, and a final full check validates everything.
So the plumber comes twice: before the screed for the pipes, after the tiling for the fixtures. The tiler works in between, which takes precise coordination.
A walk-in shower in a flat: is it possible?
Not everywhere. The trap has to be set into the floor with a slope, and on an upper floor you cannot dig into the slab above your neighbour's ceiling. When there is not enough height, an extra-flat shower tray is the best compromise: laid on the floor, it gives the level-access look with far less risk of leaks than a fully tiled shower. If the shower is tiled, waterproofing under the tiles is not optional.
The costliest planning mistakes
- Ordering fixtures before the drains are validated. A vanity unit that does not fit with the stack blocks the whole job.
- Changing the layout after the pipes are run. The wall chases have to be redone and the schedule slips.
- Neglecting ventilation. A bathroom without proper extraction builds up damp and grows mould within months. Our article on damp on the ceiling explains how to tell condensation from a leak.
- Skipping the pressure test to save half a day.
- Rushing the drying times, the second big source of defects.
Co-ownership constraints
In an apartment building (a copropriété, run by a property manager called the syndic), a bathroom is not just your business:
- work on the soil stack, or moving a waste that connects to it, affects the common parts and needs the co-ownership's prior approval;
- a water cut that affects other flats must be coordinated with the syndic and announced to residents;
- the co-ownership rules set the hours for noisy work.
Planning for these avoids work stoppages and disputes with neighbours.
How long and what budget
A full bathroom renovation usually takes two to three weeks, with drying times that cannot be shortened. Plan somewhere else to wash if you only have one bathroom.
The budget depends mainly on the state of the existing plumbing (just replacing fixtures, or redoing the pipes), the finish (mosaic or large tiles take longer to lay) and the fixtures (a concealed thermostatic shower valve costs more than a standard mixer). Insist on a quote itemised line by line rather than a single lump sum. For a rough idea of our call-out work, see our prices.
If the renovation adapts the home for older age or disability, for example replacing a bath with a safe walk-in shower, the MaPrimeAdapt' grant may be available under conditions. Check before signing the quote.
FAQ
Can a toilet be moved anywhere?
No. A toilet waste needs a specific diameter and slope to the soil stack. A big move often means raising the floor or fitting a macerator, to be decided before the layout is fixed.
Should all the plumbing be redone during a renovation?
Not always. But if the pipes are old and already exposed, replacing them costs little compared with coming back later and breaking new tiles.
Is a walk-in shower possible in every flat?
No. It needs enough depth under the finish for the slope. In some older flats, an extra-flat tray is the only sensible option.
When does the tiler come in relative to the plumber?
Between the plumber's two visits: after the pipes are run and pressure tested, before the fixtures are fitted.
Plan your renovation with a plumber
Réseau Tubulure supports bathroom renovations in Paris and the inner suburbs (92, 93, 94), from feasibility to final connection. We also handle emergencies 7 days a week, 24 hours a day. Many of our plumbers speak English.
- Phone: +33 6 86 08 78 68 (06 86 08 78 68 from a French phone)
- Form: contact us
- WhatsApp: from the button on the site